Sport field renovations works
Council contractors are currently renovating sport fields after heavy use throughout the winter season. Works include the removal of compacted and worn areas (soil and old turf milled and redistributed to other parks within Mosman), relevelling of playing surface, returfing and topdressing. A total of 14,000 square meters of turf will be laid and 328 tonnes of 80/20 topsoil (80% sand and 20% soil per tonne). Ovals will be available for use for the summer season from 1 October 2018.
Middle Head Oval is excluded from the above, as the playing surface will be redeveloped with works commencing early September. All stakeholders have been advised and works on Middle Head Oval are expected to be completed by December 2018 with it available for use from the end of January 2019.